Sanctioned in December 2015, the project aims to connect Mumbai and Ahmedabad with a 508 km high-speed rail corridor, ...
The Mumbai-Ahmedabad High-Speed Rail (MAHSR) project, India’s first bullet train corridor, has achieved 47.17 per cent ...
This segment features extensive infrastructure, including a 124.027 km-long viaduct and bridges, 36 crossings (with 12 steel ...
India is making significant strides with its first undersea rail tunnel, part of the Mumbai-Ahmedabad High-Speed Rail ...
India is looking to run a high-speed Vande Bharat train on the country’s first bullet train route between Mumbai and ...
Work is well under way on the 316-mile high-speed line connecting Mumbai with Ahmedabad in Gujarat province. The huge project ...
The highly anticipated Mumbai-Ahmedabad bullet train project is set to revolutionise India's transportation eco-system in ...
India is considering deploying its own high-speed Vande Bharat trains on the Mumbai-Ahmedabad bullet train corridor after missing the deadline for the project's launch, Business Today reported. The ...
The Mumbai-Ahmedabad bullet train project, initially targeted for 2026, is now facing potential delays until 2030. Designed ...
As per the plan, the indigenously built Indian Bullet train with 280 kmph maximum speed will run from 2030 to 2033 between ...
The project aims to match European and Japanese standards, offering high-speed travel like never before in India ...
The Indian Railways said the plan is to start fully-functional operations of Vande Bharat trains on this track by 2027, to ...